N3.6tr rail contract bypasses FEC approval


(0 Likes)
The N3.6 trillion ($12 billion) standard coastal
railway line contract awarded before the 2015
elections did not follow regulations guiding
contract award, a House of Representatives
committee has revealed in an interim report.
The contract was awarded by the government of
former President Goodluck Jonathan to the
Chinese construction giant, CCECC.The rail line is to run from Calabar, through the
president’s native village of Otuoke in Bayelsa
State to Lagos.
However, the interim report of the House Ad-hoc
committee, which is investigating railway
contracts from 2010 to 2014, has unearthed serial
breaches of the Public Procurement Act and other
laws.
The committee, chaired by Rep Johnson Ehiozuwa
(PDP, Edo), was set up to investigate the activities
of the Federal Ministry of Transport, the SURE-P
programme and the management of Nigerian
Railways Corporation from 2010 to 2014.
A scrutiny of the 20-page report, exclusively
obtained by Daily Trust, shows that almost 40
railway contracts reviewed were breached in one
way or the other.
The anomalies range from multi-billion contracts
awarded without competitive bidding; contractors
without verifiable cognate railway experience or
using the names of international companies to
secure contracts but executed without their
involvement.
The report is also replete with evidence of
contracts awarded without proper
documentation and at inflated costs, as well as
contract manipulation without the involvement of
the Board of the Nigerian Railway Corporation.
In the case of the N3.6 trillion costal rails the
report revealed that there was no competitive
bidding even as the cost was inflated.
Also, there was no cogent feasibility study or
independent technical assessment or advice and
no front end engineering design (FEED) or even
preliminary design, the report said.
It is mandatory for major contracts to get the
approval of the Bureau of Public Procurement
(BPP), but in this case the bureau had refused to
approve the contract because the cost was
inflated and there was no funding plan.
 Contracts also routinely must be approved by
the Federal Executive, but the council was
bypassed this time around.
The Jonathan government allegedly went ahead
and signed the contract even without the
approval of both the bureau and the FEC, the
report said.
“FMT (Federal Ministry of Transport) entered into
a commercial contract with CCEEE/CRCC on
November 19, 2014. The award did not obtain a
‘no objection’ certificate from the BPP due to the
absence of a verifiable funding plan”, the report
stated.
It added: “It was not presented to FEC (Federal
Executive Council) and there was no
constitutional approval for this contract; indeed
the contract was signed a week after the BPP
refused a ‘no objection’ certificate and insisted it
was overpriced.”
This, according to the report, is contrary to the
preamble in the contract document which claims
that all due process steps were complied with and
that the BPP issued a no objection certification
no: BPP/DG2014/2162 dated November 12, 2014.
“An examination of the records indicates that a
letter bearing the same reference number and
same date was written to the Minister of
Transport by the BPP giving reasons a no
objection certificate could not be issued”, the
report stated.
The report said the preamble clauses in the
contract document further disclosed that the
former President (Goodluck Jonathan) granted
anticipatory approval for the award of the
contract vide a letter with reference number:
Pres/99/MT/203 dated November 17, 2014.
“In the absence of sight of the purported
presidential letter, no comment can be made on
its adequacy save that, there is no provision in the
Procurement Act for anticipatory approvals,” the
report stated.
The CCECC had told the committee that work was
yet to commence and that no payment had yet
been made.
 However, the committee feared that certain
caveats in the contract may not adequately
protect the current government from financial
liability if it decides to stop the contract or is
unable to find the $12bn required to fund it.
 Other railway projects
The report also provided the status of other
railway projects awarded between 2009 and 2014.
These include the Kaduna to Idu standard gauge
contract also awarded to CCECC on October 22,
2009 at the cost of $849million for a period of 4
years. Its consultancy was awarded to TEAM for
$318million.
However, work did not begin until February 2011.
On May 13, 2015, there was a variation in cost
shooting the total sum to $1.04billion while the
completion date was extended to December 31,
2015, a date which has not been achieved, the
report noted.
While the Ministry of Transport told the
committee CCECC had to date been paid
$769.8million, the contractor said it had received
$792million.
Also, the committee report revealed that site
operations were yet to commence on the Lagos –
Ibadan standard gauge contract which was
awarded to CCECC on August 28, 2012 to be
executed in 36 months. The contractor claimed it
was yet to receive any money in respect of the
contract which is about 40 months late.
Among past chairmen of the NRC who were
invited by the ad-hoc committee to explain their
roles in the award and implementation of the
contracts were: Alhaji Bamanga Tukur
(2014-2015); Alhaji Kawu Baraje (2011-1013);
Ambassador Ladan Shuni (2011) and Alhaji Bello
Mohammed Haliru (2009-2011).
While Alhaji Bello was said to have failed to
attend the committee’s hearing, Tukur and Shuni
were said to have attended. “Each took turn to
disown any involvement in the award of contracts
at the NRC. Ambassador Shuni ...also denied the
existence of any report in respect to any such
investigation”, the report said.
Although the committee described its interim
report as “report of an investigation in progress”
and offered no recommendation, a member of
the committee who spoke with Daily Trust in
confidence said: “This is only a tip of the iceberg
because we have not even started the technical
review to look into the execution of the contracts.
“All we have reviewed so far are the contract
documents and not the physical work to see
whether the work has been done or not, if it is
true when they tell us that they have completed
90% of the work and paid the contractor. What
we know is that the contractors have all but one
disappeared into thin air,” it said.

Comments

Popular Posts